For a construction site to qualify for the rainfall erosivity waiver, the cumulative rainfall erosivity over the project duration must be less than five and the site must be stabilized with at least a 70 percent vegetative cover or other permanent, non-erosive cover. The rainfall erosivity must be calculated according to the method in U.S. EPA Fact Sheet 3.1 Construction Rainfall Erosivity Waiver dated January 2001 [PDF 1,855K].

If it is determined that a construction activity will take place during a time period where the rainfall erosivity factor is less than five, a written waiver certification must be submitted to Ohio EPA at least 21 days before construction activity is scheduled to begin. If the construction activity will extend beyond the dates specified in the waiver certification, the operator must either: 

  1. recalculate the waiver using the original start date with the new ending date (if the R factor is still less than five, a new waiver certification must be submitted) or
  2. submit an NOI application form and fee for coverage under the Construction Storm Water general permit at least seven days prior to the end of the waiver period.

For guidance, please see USEPA’s Small Construction Activity Waivers page.

The Waiver Certification requires a topographical map. Here are two links which can be used to obtain a topographical map:

If your construction site does qualify for the rainfall erosivity waiver, submit the Low Erosivity Waiver Certification form [PDF 402K] to Ohio EPA (Do Not Mail the form to USEPA) at the following address:

  Ohio Environmental Protection Agency
Division of Surface Water
Attn: Mike Joseph
P.O. Box 1049
Columbus, Ohio 43216-1049

For Additional Information

If you have questions about this program, see the Storm Water Program Contacts page.

 

* Although Ohio EPA cannot endorse, sanction or guarantee the accuracy of information found on external Web sites, we think you might find these outside links useful. When you select a link to an external Web site, you are leaving Ohio EPA's Web site and are subject to the privacy, security and accessibility policies of the owners/sponsors of the external site.
 

* Adobe Acrobat Reader is required to view the [PDF] publications. If you do not have Adobe Acrobat Reader, click here to download it for free.
 

Ohio EPA logo

Contact the Division of Surface Water
Mailing Address: P.O. Box 1049, Columbus, OH 43216-1049
Street Address: 50 West Town Street, Suite 700 Columbus, OH 43215
Phone: (614) 644-2001 ~ Fax: 644-2745 ~ E-mail
Emergency Response Hotline (800) 282-9378